Fiscal_Year 2014 Deadlines for Submission of Wyoming Purchase Requisitions

IM WY 2014-029
Instruction Memorandum

United States Department of the Interior
BUREAU OF LAND MANAGEMENT
Wyoming State Office
P.O. Box 1828
Cheyenne, Wyoming 82009-1828
IN REPLY REFER TO:
1510 (951) P
June 6, 2014
EMS TRANSMISSION: 6/6/2014
Instruction Memorandum No. WY-2014-029
Expires: 09/30/2015
To: All Employees
From: State Director
Subject: Fiscal_Year 2014 Deadlines for Submission of Wyoming Purchase Requisitions
Program Area: Acquisition and Engineering
Purpose: This Instruction Memorandum (IM) establishes Fiscal_Year (FY) deadlines for
submission of Wyoming purchase requests/complete packages. These deadlines will ensure that
State Office and District Procurement Staff have the necessary time required to provide quality
and timely service to customers.
This IM also establishes the deadlines for submitting construction projects that require
engineering review. All construction and service projects over the $25,000 threshold must be
reviewed by the State Engineer. It is policy that draft packages be submitted to the State
Engineer at least three weeks prior to the deadline dates shown below. The State Office or Field
Office Engineers will provide the review and comments to the requisitioner within 10 working
days from the time the project is received for review.
Policy/Action: Type of
Acquisition
Deadline Acquisition Lead Time *
Contracts between $100,001 and
$500,000
6/26/2014 10 weeks
Inter-and-Intra Government
Orders
6/26/2014 4-8 weeks
New Assistance Agreements 6/26/2014 8 weeks
Task Orders to Existing
Agreements
7/11/2014 4 weeks
Contracts between $25,000 and
$100,000
6/26/2014 8 weeks
Policy/Action: Type of
Acquisition
Deadline Acquisition Lead Time*

2
Orders against and existing
contract-technical & price
6/27/2014 6 weeks
8(a) Contract 6/27/2014 6 weeks
Purchase Orders between $2,500
and $25,000 (Construction and
Service)
6/27/2014 6 weeks
Purchase Orders between $2,500
and $25,000 (Supplies)
7/11/2012 4 weeks
Acquisition Lead Time – The estimated time required to process the acquisition from receipt of a
complete acquisition package, including a purchase requisition, statement of work and all
required approvals. The acquisition lead times are under optimum conditions, assuming no
clarification and/or revision of the procurement request is necessary. Additional lead time may
be required if this is not the case.
Time Frame: Effective immediately.
Coordination: This IM was coordinated between the State Procurement Analyst, the State
Engineer and the Business Manager, WY-951.
Contact: Questions should be directed to Matt Burns, Procurement Analyst, at 307-775-6056.